The annual drawdown of Galway Lake will start October 20, 2025. The drawdown will continue until on or about December 1, 2025, and will drop the lake level 7 feet from normal operating level. If planning pontoon or other boat removal at the GLCA boat launch, please schedule it accordingly by contacting Kurt Ladu at 518-571-9413.

During this year’s drawdown, GLCA is expecting to perform significant relining and repair work on the discharge tube at the dam tower, so, depending on schedules, there might be some minor fluctuations in the drawdown. The Board wanted members to be informed in advance that this might occur and is not an indication of any issues in this procedure. Once the lake drawdown is complete, the lake will be held at this level until January 19, 2026, at which time the refill will commence. The lake will be brought up to the winter gate and held at this level until the ice leaves the lake. Please be aware that with changing levels of the lake the ice should be considered hazardous to use and we ask that you stay off the lake during this transitional period.